Click to Return to RVeCafe Homepage

2004 Teton Homes

Return to main menu




Saturday, May 16, 2026: Got a few things replaced and improved on this rainy day. The Teton has two furnaces. The bedroom furnace thermostat looks like the photo at left. Probably the 2004 original. I replaced it with a modern Honeywell digital. Click the left photo to see the replacement. The Teton has two large propane tanks but no easy way to know their level so I added gauges. Click on that photo to see the TV I installed in the bedroom. The story is: I purchased the TV at St. Vincent de Paul charity shop for $32. As it turned out, it is identical to a TV we donated to the Bouse Community Center many years ago. I intended to use it for DVD viewing but did not like the quality of the video from the old DVD player. So I moved the TV to the bedroom and intend to install a Roku stick for streaming.





Tuesday, May 12, 2026: My morning began early. I met with George (the previous owner) at 7:30 when we drove together to the Oregon DMV in Roseburg to transfer the title from George to Gwen and Me. That literately took only 5 minutes and $101. George asked to visit Lowes for a quart of paint. While George was getting paint, I bought screen door material and a door protector. That set my project for the rest of the day. I made a mistake by shutting Dave inside the Teton before he recognized it as his new home. So he tore the screen wanting out. There aren't many flies and wasps yet but I want the screen door repaired before they arrive. Click each photo for more views. 


Sunday, May 10, 2026: I invited Glen and Kenny Lee to dinner tonight so I needed to get a few thing finished before they arrived. I quickly learned I needed a second set of hands to get the new LED light fixtures installed. The old florescent lamps did not produce much light and were very hot when on. These new LED lights produced a lot of light and cool in use. Glen helped by holding the fixture in place while I set the screws. Click that photo to see all four LED fixtures installed. The AC intake filters needed to be cleaned. I rinsed out the dirt. Click that photo to see how well they cleaned up. 







May 5, 2026: This was a long hard day. The Teton got moved to my lot. It took Bud and Anita an hour to get it situated just right to match the awning placement. Then it had to be leveled. Once everything was set, Gary and Travis began installing the overhead panels. I would clean the panel then deliver to Travis and Gary.  They would secure the panels then move to the next. They worked fast, took about 3 hours to finish the entire project. Randy picked up the steps and delivered in front of the door.  Click on all the photos to see more views.



Monday, May 4, 2026: George and I installed the awning posts today. They are anchored to the base blocks and to the block wall exactly as they were mounted on George's lot.

Tomorrow morning, my friend, Bud will hitch to the Teton with his Ford F350 dually and bring it around to my lot. The Teton must be exactly 10' 4" from the block wall. Whoever installed the block wall did not get it parallel to the concrete pad. I have marked where the Teton wheels must be with a neon pink tape. The overhead line in the photo is the line Dave is connected to so he has some freedom of movement. It does not appear it will be in the way of the awning installation. Click both photos for more views.



Saturday, May 2, 2026: I placed the five base blocks today for the awning support posts. Each block must be in the exact location as they were when located on George's lot. But the blocks from front to back can't be level because we want the rain water to flow downhill to the street. After placing the first block (left photo) I stretched a line to the lost block location so that each block toward the rear would be a little higher. Now the rain water will flow toward the street. George will drill each block for the bolts to attach the posts. Click both photos for another view.

Friday, May 1, 2026: Five holes must be dug for the bases to support the five poles supporting the awning. I have pavers, a drain pipe and a treated 2 x 4" in the way of a simple hole. George will deliver the base blocks tomorrow so I can know how deep to make the holes and how wide to make the cut in the 2 x 4".  Travis will have to drill the holes for the bolts and then the reassembly of the awning will begin.





Thursday, April 30, 2026: A lot of help showed up today to remove and move the awning. I removed all the screws anchoring the panels to the support beams. Travis did all the roof top work, Gary removed the panels and handed them to George who put them onto his trailer. With all the help, it only took 2.5 hours to have everything into the trailer. I hope erecting the awning on my lot goes as quickly. Click each of the photos for another view.



Wednesday, April 29, 2026: So it begins. A new to us RV will need to be improved to match our lifestyle. This first thing is simple. The Teton had no table for meals or for computer although I may shop for a computer desk some day in the future. I have notice a few things in my first walk through which I would want to improve/change. Anyway, I found this table on Facebook Marketplace and picked it up today. I paid too much but it is the style I like. The chair fabric was dirty so I gave them a shampoo. My intention is to reupholster them but I would want Gwen to chose the fabric. Until then, the shampoo will have to do. Notice Dave watching from the backseat. Click both photos for another view.















eturn to RV Trips Copyright, 2024 by RVeCafe.com